11.11.24 - GROUND BREAKING
THE PROJECT:
ONE
TWO
THREE
MAINTENANCE
CTE AND ART
FITNESS
Projects would include A roof replacement at Pewaukee Lake (life cycle ends 2024-25) and B Horizon Elementary (life cycle ends 2025-26). HVAC C would also need to be replaced at portions of Pewaukee High School as they are original to the building. Finally, by installing D solar panels, the district will be able ot reduce the future energy costs for building operations. Flooring will be replaced at Horizon Elementary as well.
Additions and renovations would occur at Pewaukee High School (PHS) to update Career and Technical Education and Art learning spaces which have not been largely touched since PHS’s construction in 1968. This would include a STEAM Innovation Hub, metals, woods, art, graphic design, engineering, fashion, and culinary.
Physical Education and fitness spaces would need to be relocated A to allow for the renovation of the Career and Technical Education and Art facilities. This includes shifting the current weight room, boys locker room, storage, and classroom/office spaces south. Parking would also then need to shift south, pushing the practice field to the east. B
THE TIMELINE:
FALL
2024
Site work
& relocation of Lot 5
SPRING
2025
Start of
construction
SUMMER
2026
Completion
of overall
project
FALL
2025
Completion
of Fitness
portion of
project
The Pewaukee School District is dedicated to responsibly managing its facilities and resources to provide students with dynamic learning experiences that prepare them for future success. Before the approval and construction on our current project, the district has undertaken a strategic process for facility planning and improvement, as outlined in the following highlights:
​
-
December 12, 2022: Presentation of the Long-Range Facility Plan to the Board of Education.
-
April 17 and May 15, 2023: Community events focused on facility and strategic planning.
-
August 21, 2023: Engagement of Eppstein Uhen Architects and CG Schmidt for the Facility Master Plan process.
-
October 10, 2023: Launch of a community survey regarding the facilities plan.
-
January 15, 2024: Approval of the referendum question for the ballot by the Board of Education.
-
April 2, 2024: Pewaukee community votes to pass the facility referendum.
​
This timeline reflects the district's commitment to ensuring that its facilities meet the needs of both current and future students while upholding its mission to "Open the Door to Each Child’s Future."